Tuen Mun - Chep Lap Kok Link, Southern Viaduct Section

Gammon Construction

Production of a very detailed Design claim which dealt with thousands of design submissions over a 4 year period, identifying all delays and allocating delays to the delaying party. Assessing entitlements to prolongation costs incurred during a two year critical delay.

YEAR
2018-2019

ROLE
Consultant

PRINCIPLE ELEMENT
Roads

DISPUTE TYPE
Mediation

CONTRACT TYPE
HK Government

LOCATION
HK

VALUE
HK$8.6b